Chiller Plant Control: Sequencing, Resets and kW/ton
Chiller plant control is the set of decisions that determine how much electricity a central cooling plant uses to deliver a ton of cooling. Five decisions do most of the work: how many chillers run, which one leads, what temperature the chilled water leaves at, what temperature the condenser water enters at, and how much water flows. The machines are rarely the problem. The sequence is.
That’s why two buildings with identical chillers can run at 0.65 and 0.95 kW/ton. Same equipment, same weather, same load. Different staging logic, different reset limits, different bypass behaviour on a Tuesday afternoon.
This guide covers the five decisions, the code clauses that constrain them, the trade-offs that decide the set points, and the five failures that survive commissioning because nobody trended the right points. It’s written for the person who has to make an inherited plant behave, not for someone shopping for a chiller. The wider architecture is in our guide to HVAC control systems.
Already commissioning a plant and want the sequence reviewed against the clauses below? Send the sequence and the points list to our application engineers, and we’ll mark where the logic departs from the requirement.
Key Takeaways
- Plant kW/ton is set by staging, two resets and flow control, not by chiller nameplate efficiency.
- ASHRAE 90.1-2022 requires variable flow with a 25% turndown, differential pressure reset on valve position, isolation of idle chillers, and automatic chilled water temperature reset above 300,000 Btu/h.
- Fixed condenser water set points are the most common avoidable loss. One 1,000-ton plant moved from a fixed 83°F to a variable set point and cut its plant energy from 0.92 to 0.67 kW/ton.
- Resets must be limited and sequenced against each other, or they oscillate. Most reset failures are two loops chasing the same valve.
- A sequence is only proven by trends: plant kW/ton, valve position, approach, and flow, recorded at 15-minute intervals and reviewed monthly.
What Chiller Plant Control Actually Decides

A chiller plant is everything between the building’s chilled water coils and the cooling tower: chillers, chilled water pumps, condenser water pumps, cooling towers, and the valves and sensors that connect them. Plant efficiency is measured in kW/ton, the total electrical demand of all of that equipment divided by the tons of cooling actually delivered.
A chiller at 0.48 kW/ton inside a plant at 0.92 kW/ton is doing its job. The other 0.44 kW/ton is pumps, towers, and decisions.
| Decision | Control question | What it moves |
|---|---|---|
| Chiller count | How many machines are needed for the current load | The largest single block of plant power |
| Lead machine | Which chiller runs first and which is staged next | Efficiency at part load, run hours, wear |
| Chilled water set point | What supply temperature the plant holds | Compressor lift and coil performance |
| Condenser water set point | What entering water temperature the tower delivers | Compressor lift against tower fan energy |
| Flow | How much water moves and through which path | Pump power, delta-T, and whether chillers stay loaded |
The code sets a threshold at which these decisions have to be made by a building automation system rather than by hand. ASHRAE 90.1-2022 requires DDC for a chilled water plant serving more than three zones with a design cooling capacity of 300,000 Btu/h or more. For larger plants, it also requires kW/ton metering, trended every 15 minutes and kept for 36 months.
Those numbers matter for a practical reason. If the plant is above the threshold, the meters and trends already exist by code. The sequence can be judged against them instead of argued about.
Sequencing and Staging: Which Chiller Runs Next
Staging is the decision with the largest effect and the least agreement. Two families of logic exist, and most plants use neither deliberately.
| Logic | How it decides | What it needs | Best when |
|---|---|---|---|
| Load-based | Stages another chiller when the running machines pass a load threshold for a set time | A reliable load calculation and a timer | All machines are the same type, size, and age |
| kW/ton-based | Compares the measured efficiency of the running set against the next set at the current load | Per-chiller power metering and a controller that can do the comparison | Machines differ in type, size, or age; the normal case after a partial retrofit |
The physical facts that constrain both:
- Every chiller has a minimum load below which it either surges, trips, or cycles. A machine that is staged on for a 40-ton load in a 400-ton plant will short-cycle until it’s staged off again. Sequencing has to respect the manufacturer’s minimum, not just the plant total.
- Chillers piped in series for a higher temperature differential count as one chiller for isolation purposes, which changes how the sequence treats them.
- With constant-speed chilled water pumps serving multiple chillers, the pump count must be no less than the chiller count, and the pumps must be staged with the chillers. A pump left running through a shut chiller is a short circuit.
- Idle chillers must have their flow automatically shut off. ASHRAE 90.1-2022 §6.5.4.3.1 requires provisions so that all fluid flow through a chiller stops when that chiller shuts down.
Two settings decide whether any staging logic behaves. One is a load dead band, wide enough that the plant doesn’t stage a machine on and immediately off again. The other is a time delay, long enough for the new machine to load and temperatures to settle. A good algorithm with no dead band will hunt; a simple algorithm with a generous dead band will hold.
Lead and lag need a rotation rule. Running the same chiller first for years concentrates wear and leaves the standby machine unproven. Rotate on run hours, not calendar dates, and at a load point where the changeover is safe.
Chilled Water Temperature Reset

The chilled water supply temperature is usually set at design conditions and then left there for years. That’s the second avoidable loss.
The physics is straightforward. A warmer chilled water supply raises the evaporating pressure, which lowers the pressure lift the compressor works against, which reduces compressor power. The same reasoning runs through the condenser water reset in the next section.
The cost lands on the air side, in three places:
- Every coil needs more flow or more air to deliver the same cooling, so pump and fan energy rise.
- In a humid climate, a coil that runs too warm stops condensing moisture, and the space drifts above its humidity limit.
- Terminal valves open further to compensate, which removes the position margin the reset itself depends on.
That’s why the reset needs a lower limit and a humidity interlock, not just a warm-water schedule.
ASHRAE 90.1-2022 §6.5.4.4 sets the requirement for systems above 300,000 Btu/h serving comfort conditioning: controls must automatically reset the supply water temperature by representative building loads, including return water temperature, or by outdoor air temperature. Where DDC controls the valves, the set point must be reset on valve position until one valve is nearly wide open.
That last clause is the useful one in practice, because valve-position reset is self-correcting. If every valve is half closed, the water is colder than the building needs, and the set point can rise. If one valve is nearly wide open, the plant is at its limit, and the set point should stop rising. The sequence is driven by the building’s own demand rather than by an assumed load curve.
The failure mode is a reset with no dead band and no rate limit. A set point that moves on every valve-position change will oscillate, and the chillers follow it. Reset in small increments, with a wait of several minutes between steps, and hold the set point whenever the plant is staging.
Condenser Water Reset and the Tower Trade-off
Condenser water is where the largest measured savings in the literature come from, and where the trade-off is easiest to explain.
A lower entering condenser water temperature reduces the condensing pressure, which reduces lift, which reduces compressor power. But producing colder condenser water costs tower fan energy and, in a fixed-flow plant, condenser pump energy. There’s an optimum somewhere between the two, and it moves with wet-bulb temperature and load.
PNNL’s re-tuning guide describes the trade-off directly: the condenser water set point is “a tradeoff between reducing power input to the chiller’s compressor by reducing the condensing temperature and pressure, and reducing power to the cooling tower fans by increasing the condenser water temperature” (PNNL-29078). It also notes the obvious failure: a set point below what the ambient wet bulb can deliver raises tower energy without lowering the water temperature at all.
The measured case is worth quoting in full because it’s unusually clean. ACHR News reported a 1,000-ton VFD chiller that had run for six years with a fixed 83°F entering condenser water set point. At 444 tons, it ran at 0.77 kW/ton on the chiller and 0.92 kW/ton for the plant, at $34.12 per hour.
After the set point was made variable, down to 55°F when conditions allowed, the same plant at 453 tons ran at 0.48 kW/ton on the chiller and 0.67 kW/ton for the plant, at $25.75 per hour. That’s a 27% improvement in plant efficiency from one control change (ACHR News).
Two limits decide how far the reset can go. The chiller manufacturer sets a minimum condenser water temperature below which the machine won’t run stably, and the tower has an approach temperature below which it can’t drive the water any closer to the wet-bulb. Both belong in the sequence as hard limits, not tuning values.
Tower staging interacts with the reset. Running all cells in parallel at low flow beats running fewer cells at high flow, which is why ASHRAE 90.1-2022 §6.5.5.4 requires open-circuit towers on water-cooled systems to run all cells in parallel at the larger of the smallest pump’s minimum expected flow or 50% of the cell’s design flow. Valve selection for that duty is covered in the cooling tower butterfly valve guide.
Flow: Variable Primary, Primary-Secondary and Bypass
Flow architecture decides whether the resets can be delivered. The two common arrangements behave very differently at part load.
Primary-secondary keeps constant flow through the chillers and varies flow in the secondary loop, with a decoupler between them. It’s reliable and easy to stage, and it has a well-known failure: when secondary flow falls below primary flow, the surplus primary water crosses the decoupler and returns to the supply, raising the chilled water temperature the coils receive. The plant looks like it’s failing while every chiller runs normally.
Variable primary flow varies the flow through the chillers themselves. It uses less pump energy and avoids the decoupler short circuit, but it needs a minimum flow path through every operating chiller. That’s what the bypass valve is for: when the terminal valves close and flow drops toward the evaporator minimum, the bypass opens to keep the chiller safe. A bypass that sticks open does the opposite, sending supply water back to the return and unloading the plant while the building goes warm.
ASHRAE 90.1-2022 §6.5.4.2 requires variable flow for chilled and hot water systems with three or more modulating or stepping valves, with the ability to reduce pump flow to no more than the larger of 25% of design flow or the equipment minimum (UpCodes). It also requires differential pressure to be measured at or near the most remote heat exchanger, the set point to be no more than 110% of what design flow needs, and, where DDC is used, the set point to be reset downward on valve position until one valve is nearly wide open.
That clause makes the differential pressure transmitter a control input, not a gauge. It has to be accurate enough at low differential to drive a reset, which means a transmitter specified for the range, not chosen by pipe size. The differential pressure transmitter range covers 0-10 kPa to 10 MPa with accuracy of ±0.075%, turndown to 100:1, and 4-20 mA, RS485, or HART output.
The control valve at each terminal is the other half of the loop. A valve that’s oversized for its coil spends its life in the first 10% of travel and can’t give the reset a usable position signal. That’s a sizing question, covered in the control valve sizing guide. For plant isolation duty, the large-bore electric butterfly valve range runs from DN50 to DN500 at PN16, with a 1,200 kPa maximum differential and 4-20 mA, RS485 or M-Bus control.
If you need, please read our article on fan coil control valve arrangement.
The Points That Prove the Sequence Works

A plant sequence is a hypothesis until it’s trended. The code already requires the basic dataset above the metering thresholds, and the same points prove a sequence in a plant below them.
| Point | Why the sequence needs it |
|---|---|
| Plant kW and tons, or kW/ton | The outcome being controlled; without it, staging is guesswork |
| Per-chiller kW | Shows which machine is efficient at the current load |
| Chilled water supply and return temperature | Delta-T reveals low-load, bypass, and sensor problems |
| Condenser water entering and leaving temperature | The reset’s actual result against its set point |
| Chilled water flow | Turns temperatures into tons, and exposes short circuits |
| Most-open valve position | The reset input that code names explicitly |
| Differential pressure at the remote sensor | Confirms the pump is meeting the real load |
| Tower fan speed or stage | Separates chiller savings from tower cost |
| Outdoor air temperature and humidity | The context that makes any kW/ton number comparable |
Two habits turn these points into control. Review plant kW/ton monthly against outdoor air temperature, so a seasonal change isn’t mistaken for a fault. And review the most-open valve position distribution, because a plant whose valves all sit below 40% is a plant whose chilled water is colder than it needs to be.
Thermal energy meters close the loop on the denominator. An ultrasonic heat meter with Class 2 accuracy and a 100:1 range ratio measures delivered energy directly, which beats inferring tons from flow and temperature in software. Balancing valves keep the flow where the design put it, so the plant sees real demand; the balancing valve range covers DN15 to DN350.
Five Failures That Survive Commissioning
These are the patterns that pass a functional test and still cost energy for years.
| Failure | What you see | Fix |
|---|---|---|
| Staging with no dead band | The plant stages a chiller on, the new machine loads, the temperature falls, the machine stages off, and the cycle repeats | Add a load dead band, a time delay, and hysteresis on the staging threshold |
| A bypass left open | A variable primary plant serves itself instead of the building at low load | Check bypass position at low load, when it should be modulating |
| Two resets fighting | Chilled water reset chases the most-open valve while condenser water reset chases a wet-bulb curve, and neither settles | Sequence them: hold one while the other moves |
| One bad sensor driving the plant | A temperature sensor reading a degree high moves the whole reset a degree | Calibrate the plant sensors at commissioning and recheck when the sequence behaves oddly |
| No mode logic | The sequence describes normal operation but not startup, shutdown, failure, manual or freeze protection | Write the modes first, with triggers, timings and fail positions |
The document structure that prevents the last failure is the same one used for any air-side sequence. It’s set out in the sequence of operation guide, and a plant sequence should follow it unchanged.
FAQ
What is chiller plant control?
It’s the sequence that decides how many chillers run, which one leads, what chilled and condenser water temperatures the plant holds, and how much water flows. Those decisions set the plant’s kW/ton more than the chillers’ nameplate efficiency does.
What is a good kW/ton for a chiller plant?
There’s no universal number. It depends on climate, load profile, machine type, and whether the count includes towers and pumps. The useful benchmark is the plant’s own recorded baseline at the same outdoor conditions, which is why the code requires kW/ton trending above the metering threshold.
Why do chillers short cycle?
Usually because the machine is staged below its minimum load, or because the water volume in the loop is too small for the staging logic to see a stable temperature. Warm chilled water set points at low load reduce the frequency, and a proper dead band stops the staging logic from adding to it.
What is the difference between primary-secondary and variable primary flow?
Primary-secondary keeps constant flow through the chillers and varies the secondary loop. Variable primary varies flow through the chillers themselves and needs a bypass to protect the evaporator minimum. Variable primary uses less pump energy but depends on that bypass working.
How much can chiller plant optimization save?
ACHR News cites improvements of 5% to 30% in plant efficiency through systematic monitoring and control changes, and its worked example delivered a 27% plant efficiency improvement from a condenser water reset alone. Savings depend on how far the plant has drifted from good practice.
The Sequence Is the Plant
A chiller plant is a control problem wearing mechanical clothes. The chillers, pumps, and towers are capable of a wide range of efficiency, and the sequence chooses where in that range the plant operates each hour. Staging, two resets, and flow decide almost all of it, and the code clauses exist because those decisions are too valuable to leave to habit.
Start with the trends, not the equipment. A plant that knows its own kW/ton at three outdoor conditions can be improved with confidence; a plant that doesn’t is guessing.
If you’re specifying the valves, transmitters, or meters that make the sequence possible, our application engineers can review the point list and the flow diagram and tell you where the instrumentation will limit the control you’re asking for.